The South Dakota Supreme Court issued an opinion on Thursday, June 14, that state courts don't have jurisdiction over certification of the Keystone XL pipeline permit.

Pipeline opponents appealed the Public Utilities Commission's 2014 certfication of TransCanada's 2010 permit.

On appeal, a Sixth Circuit judge upheld the certification, and opponents appealed that decision.

Now the high court says neither the Sixth Circuit nor the Supreme Court has standing under state law to hear the appeal.

Victoria Wicks file photo

The South Dakota Supreme Court heard arguments on Tuesday, April 17, from opponents and proponents of the Keystone XL pipeline.

In 2015, the Public Utilities Commission accepted TransCanada's certification that it can comply with the conditions of its 2010 permit.

Opponents appealed that certification to the Sixth Circuit Court last year, and now appeals the court's decision to the state's high court.

SDPB's Victoria Wicks has this report.

Victoria Wicks

The Keystone XL pipeline is at issue once again, this time in a South Dakota courtroom. Opponents filed an appeal in 2016 after the Public Utilities Commission gave the go-ahead for the pipeline the previous year. On Wednesday in Pierre, a Sixth Circuit judge heard oral arguments in the case.

Opponents say the PUC didn't do its job to ensure that TransCanada can build a safe pipeline.

But the PUC and TransCanada say the outcome followed state law.

SDPB's Victoria Wicks traveled to Pierre to get this report.

Victoria Wicks

At the Public Utilities Commission hearing in Pierre, a whistleblower testified earlier in the week, and Wednesday morning, TransCanada rebutted his testimony. Evan Vokes alleged TransCanada ignores regulations and uses faulty welding inspections. TransCanada says Vokes was a low-level employee without the required knowledge to make the allegations. SDPB’s Victoria Wicks reports on the hearing set to determine if TransCanada can still meet the conditions it agreed to in 2010, when the PUC first permitted the Keystone XL pipeline.

Victoria Wicks

A former TransCanada employee referred to as a whistle-blower took the stand this weekend at the Public Utilities Commission hearing in Pierre. The meeting started last Monday and continues this week. Evan Vokes testified on Saturday, and his testimony continues Monday or Tuesday, depending on scheduling of other witnesses.